FAA Lets Boeing Raise 737 MAX Production to 42 a Month (2025)
On 17 October 2025, the FAA approved Boeing's request to build 42 Boeing 737 MAX aircraft a month, up from the cap of 38 it had set after a door plug blew out of an Alaska Airlines 737 MAX 9 in January 2024.
On 17 October 2025, the US Federal Aviation Administration (FAA) approved Boeing’s request to increase production of the Boeing 737 MAX from 38 to 42 aircraft a month. It was the first time the FAA had allowed the rate to rise since it capped production in January 2024, after a door plug blew out of an Alaska Airlines 737 MAX 9 shortly after take-off. For Boeing, which earns much of its commercial revenue from the 737, the decision was an important step in its recovery.
The decision at a glance
- Date: 17 October 2025
- Regulator: Federal Aviation Administration
- Change: maximum 737 MAX production rate raised from 38 to 42 aircraft a month
- Factory: Boeing’s Renton plant near Seattle, Washington
- Background: production cap imposed in January 2024 after the Alaska Airlines Flight 1282 door-plug blowout
Why there was a cap
On 5 January 2024, a door plug, a panel that fills an unused emergency exit, blew out of an almost new Alaska Airlines 737 MAX 9 at about 16,000 ft over Portland, Oregon. No one was seriously hurt, but investigators found that bolts meant to hold the plug in place had not been reinstalled at the factory. The FAA grounded the MAX 9s with door plugs, increased its oversight of Boeing’s factories and told the company it could not raise 737 production above 38 a month until the agency was satisfied with its quality and safety systems. A long machinists’ strike in late 2024 slowed production further.
Why the FAA said yes
The FAA said its safety inspectors had carried out extensive reviews of Boeing’s production lines to make sure the higher rate could be achieved safely, and that it would keep monitoring the factory closely. The decision came weeks after the FAA had partly restored Boeing’s authority to issue airworthiness certificates for some new 737 MAX and 787 aircraft, a task the agency had taken back after the 2024 accident.
Why it matters
The 737 MAX, especially the 737 MAX 8, is Boeing’s best-selling aircraft, with thousands on order. Airlines around the world had been waiting for delayed deliveries, and every extra aircraft built each month brought cash into a company that had lost money for several years. The MAX had already been through the 2019–2020 worldwide grounding after two fatal crashes, described in our article on the 737 MAX grounding.
Boeing’s chief executive, Kelly Ortberg, said the company planned to keep raising the rate in steps of five aircraft roughly every six months, as long as its quality and safety measures stayed stable. By September 2026, he said, the 737 line was moving to 47 a month, although the step up had taken longer than expected because of supply problems with 737 wings. For the latest figures, see our report on Boeing’s October 2026 deliveries.